World Hakka Merchants Center will be completed by the end of August

The internal decoration and external garden are currently under construction.

Update: 2017-07-19 10:41:49 Source: MeiZhou Daily Hits:4

The world merchants center has dismantled the enclosure of the construction area and started the construction of exterior garden. (Photo Source: Meizhou daily, Shot by: Lian Zhicheng)

It was informed yesterday from the Meizhou Federation of industry and Commerce that the main structure of the world merchants center has been completed. The internal decoration, external garden and other related engineering works were currently under construction, which is expected to be fully completed by the end of August, and delivered by the end of September.

Yesterday, Reporters saw at the scene of the project construction of World Hakka Merchants Center that the main project of the exterior decoration has been completed, the Hakka dragon house was circular inside and square outside, with grand style and great momentum. Reporters saw at the internal construction site that the staff, dressed in uniform clothing, were carrying out the wall decoration and other related decoration works. Huang Meifa, manager of the interior decoration engineering, told that the interior decoration of the main project of world Hakka center was steadily advanced according to the construction plan, the multi-functional conference hall from 1 to 2 floor and decoration work of exhibition hall was drawing to a close, the decoration of “Entrepreneur and Innovator Center" from 3 to 5 floors were stepping up, the whole project, including external landscape engineering, was expected to be fully completed by the end of August, and accepted by the end of September. Huang Meifa said: "We will increase manpower and equipment investment, grab the deadline, and speed up the construction, to ensure complete the World Hakka Merchants Center on time.”

It is understood that the World Hakka Merchants Center covers an area of 13.67acres, 5 storeys, about 32.85 meters high, with a total construction area of 49 thousand square meters, and a total planned investment of about 500 million yuan. The project was designed by Architectural Design and Research Institute of SCUT, which was led by he Jingtang , the academician of the Chinese Academy of Engineering, and was constructed by the Aoyuan Group (Meizhou) Limited.